Delivery plan review

The canonical proposal is maintained in docs/plans/ and embedded below. It is a discussion draft; no new implementation or interface is accepted by its publication. The roadmap owns priorities and contributing describes the current workflow.

Identification and calibration delivery plan

Status: Tracker setup approved; execution details under review — revision 4, 2026-10-02. Implementation status refreshed 2026-10-12 (after the M1 acceptance review) (see implementation status). Confirmed user preferences: advance calibration alongside dynamic identification; TIAGo mocap is the first calibration reference, with TALOS contact as the second consumer/regression target. The user authorized GitHub milestone/issue creation on 2026-10-02 and requested one-by-one delivery. Tracker setup does not accept unresolved public interfaces, change solver defaults, or approve automatic implementation/merges. Review issue readiness before selecting implementation work. Existing approved work and open PRs retain their own review gates.

Purpose and scope

Deliver two trustworthy workflows within the existing package structure:

  1. Measurements → dynamic identification → physical model → held-out effort verification → inertial URDF export/reload → archived report.
  2. Measurements → geometric calibration → identifiable corrections → held-out pose/contact verification → geometric export/reload → archived report.

The workstreams proceed in parallel through focused PRs, not simultaneous edits to shared workflow classes. Their shared foundations are provenance, units/frames, explicit result stages, validation and reproducible artifacts. Dynamic and geometric solvers remain mathematically distinct.

The roadmap owns priority and milestone outcomes. This document owns the proposed work breakdown, dependencies, alternatives and review sequence. Once approved, GitHub issues own changing task status and detailed acceptance criteria. Architecture continues to describe existing code, not these proposed contracts. Existing design records remain authoritative for their scope; this plan does not supersede the modular-terms, Pinocchio-support or log-Cholesky decisions.

Evidence motivating the plan

Observation at 2026-10-02 Consequence
Core #32 reproduces missing final-joint acceleration Signal correctness precedes new dataset-based numerical claims
UR10/TIAGo sampling/filter assumptions disagree Add explicit timing and derivative provenance before refitting
Exact base-preserving SDP returns no accepted model on the three robot datasets Diagnose constraints/scaling; distinguish reconstruction from direct constrained estimation
All dataset log-Cholesky fits exhaust 200 evaluations Keep #23–#25 conditional; investigate #30 rather than promote finite candidates
Per-link projection succeeds on UR10/TX40 but changes the base fit Report it as a separate method and select exported stages explicitly
Inertial URDF first-moment/tensor handlers are stubs A file-write success cannot close physical-model delivery
Examples CI fails on missing Hey5 geometry and TALOS 3.7 held-out regression Make assets reproducible and retain numerical regression gates
Current examples have robot-specific loaders and existing reporting/export helpers Improve adapters and reuse primitives before proposing a new framework

Sources: core issues #20/#22–#25/#30/#32, core PR #31, examples issues

11/#12/#14 and PR #13 (merged 2026-10-08). The examples dynamic report and supplemental

analysis are still local additions on the PR branch. Reports include failed solver statuses and preprocessing limitations; they are not scientific go approval. Current issue/PR status must be checked when work starts.

Ownership within the current repositories

Concern Existing owner Proposed change boundary
Dynamics preprocessing and regression figaroh/identification/{identification_tools,base_identification,parameter}.py and tools/regressor.py Fix numerical contracts and expose diagnostics through existing workflow
Physical checks, projection, reconstruction identification/{physical_consistency,reconstruction}.py Keep distinct operations; add a research constrained-fit comparator before production design
Geometric preprocessing/solving calibration/{base_calibration,calibration_tools,data_loader,config}.py Fix proven problems; retain frame conventions and existing subclasses
Export and export verification tools/{urdf_exporter,export_validation,geometric_calibration_export}.py Reuse handlers/checks; complete missing inertial semantics
Reports and archives tools/{identification_report,report,compare_report,run_archive}.py, utils/results_manager.py Reuse output machinery; add explicit stage/provenance fields through an approved contract
Robot I/O and conversions figaroh-examples/examples/<robot>/utils/ CSV adapters, current-to-effort mapping and robot-specific assumptions stay here
Robot models/config/data examples/<robot>/{urdf,config,data} and shared models/ Preserve originals; document sources, frames, sample rates and redistribution constraints
Research comparisons Core private docs/development/spikes/; examples benchmarks/ Explicit source/commit dependency; never present as supported package API
Reference user workflows Existing robot entry points under examples/<robot>/ Integrate validated primitives after research acceptance; avoid a competing CLI

No TrajectoryData class was found in the current source audit. A typed data contract is a proposal, not an existing API. First inventory existing trajectory dictionaries and calibration measurement structures. Extend those or introduce one narrow type only after an ADR demonstrates two consumers, conversion rules and backward-compatible adapters. Keep dynamic trajectory samples and geometric pose/contact observations as separate payloads.

Dependency structure

flowchart TD
    R["Scope and contract review"]
    W1["<b>W1: Fixtures</b> · #33 ✅<br/>✓ ex#15 ex#16 ex#43 ex#59"]
    W2["<b>W2: TALOS regression</b> · #34 ✅<br/>✓ ex#14 ex#48"]
    W3["<b>W3: Data/result contracts</b> · #35 ✅<br/>✓ #54 #55 #125 #131<br/>✓ ex#17"]
    W4["<b>W4: Engineering process</b> · #50 ✅<br/>✓ #56 #57 #58 #73 #81–#85<br/>✓ ex#18 ex#40 ex#45 ex#50<br/>✓ ex#56 ex#60 ex#76"]
    D1["<b>D1: Acceleration correctness</b> · #36 ✅<br/>✓ #32"]
    D2["<b>D2: Signal audit</b> · #37 ✅<br/>✓ ex#19 ex#20 ex#51"]
    D3["<b>D3: UR10 truth fixture</b> · #38 ✅<br/>✓ #142 #143<br/>✓ ex#21"]
    D4["<b>D4: Physical comparison</b> · #39 ✅<br/>✓ #59 ex#12 ex#22"]
    D5["<b>D5: Convergence research</b> · #40 ✅<br/>✓ #22 (revise) #30 (no-go)"]
    D6["<b>D6: Inertial export</b> · #41 ✅<br/>✓ #60 (PR #138)"]
    D7["<b>D7: Dynamic reference</b> · #42 ✅<br/>#61✓ #116✓<br/>ex#23✓ ex#68✓ ex#69✓"]
    C1["<b>C1: Frames/data audit</b> · #43 ✅<br/>✓ ex#24 ex#25"]
    C2["<b>C2: Calibration truth/holdout</b> · #44 ✅<br/>✓ #101 #102 #105 #110 #113<br/>✓ ex#26 ex#27 ex#67"]
    C3["<b>C3: Geometric export</b> · #45 ✅<br/>✓ #62 #111 #114 #123<br/>✓ ex#28"]
    C4["<b>C4: Calibration reference</b> · #46 ✅<br/>✓ #97 #98 #99 #119 #120<br/>✓ ex#29"]
    C5["<b>C5: Calibration studies</b> · #167<br/>ex#96–#101 ex#70 ex#71"]
    D8["<b>D8: Identification studies</b> (research)<br/>#157–#161"]
    S1["<b>S1: Minimum reporting contract</b> · #47 ✅<br/>✓ #63 #70 #100 #103<br/>✓ ex#30 ex#36"]
    U1["<b>U1: Onboarding acceptance</b> · #51 ✅<br/>✓ #66<br/>✓ ex#33"]
    A["M1 acceptance review ✅"]
    S2["<b>S2: Sensitivity/uncertainty</b> · #48<br/>✓ #107<br/>open: #64 ex#31"]
    S3["<b>S3: Improved experiment design</b> · #49<br/>#65 #90<br/>ex#32"]
    S4["<b>S4: Selective composition</b> · #52<br/>#67"]
    B1["<b>B1: Backend parity</b> · #53<br/>#68<br/>ex#34"]
    LC1["<b>LC1: Log-Cholesky production</b> · #20<br/>#155 (go gate)<br/>#23 #24 #25<br/>ex#11"]

    R --> W1
    R --> W2
    R --> W3
    R --> W4
    W1 --> D2
    D1 --> D3
    D2 --> D3
    D3 --> D4
    D4 --> D5
    D6 --> D7
    D4 --> D7
    D5 -. optional nonlinear path .-> D7
    D5 --> LC1
    W1 --> C1
    W2 --> C1
    C1 --> C2
    C2 --> C3
    C3 --> C4
    C4 --> C5
    D4 --> D8
    C5 -. more worked studies .-> U1
    W3 --> S1
    S1 --> D7
    S1 --> C4
    D7 --> U1
    C4 --> U1
    D7 --> A
    C4 --> A
    U1 --> A
    A --> S2
    S2 --> S3
    A --> S4
    W3 --> S4
    A --> B1

    classDef cleared fill:#c8e6c9,stroke:#2e7d32,stroke-width:2px,color:#1b5e20
    classDef ready fill:#fff3cd,stroke:#b8860b,color:#5c4400
    class R,W1,W2,W3,W4,D1,D2,C1,C2,C3,S1,D6,C4,D3,D4,D5,D7,U1,A cleared
    class LC1 active
    classDef active fill:#fff3cd,stroke:#b8860b,stroke-width:3px,stroke-dasharray:6 3,color:#5c4400

Legend: green ✅ = tracker cleared (closure record confirmed); amber = ready, all prerequisites cleared (dashed amber border = work in progress or in review); uncoloured = blocked on an upstream package. Each box lists its tracker number, then the issues in its milestone (core first, then ex# = figaroh-examples). Issues marked ✓ are closed; unmarked issues are open. Two open examples issues have no package yet: ex#70 (TIAGo suspension real-data fit) and ex#71 (TIAGo backlash surface); both are research examples outside M1.

Implementation status

Status as of 2026-10-12, taken from the GitHub trackers. The trackers stay authoritative; refresh this table when a tracker closes.

Package Status Closed Delivered by / remaining
W1 fixtures ✅ Cleared 2026-10-03 examples #44, #57, #61, #62: hosted examples CI on both Pinocchio profiles; every robot loads from a clean checkout
W2 TALOS regression ✅ Cleared 2026-10-03 examples #46, #54: examples #14 explained; deterministic TALOS fixtures and noise-floor held-out checks
W4 engineering process ✅ Cleared 2026-10-03 core #71, #74, #80, #86–#93; examples #37, #40, #47: templates, real-model regressor tests, lint debt removed, full pre-commit blocking
D1 acceleration ✅ Cleared 2026-10-02 core #69 (fixes #32)
D2 signal audit ✅ Cleared 2026-10-03 examples #19/#20 UR10 and TIAGo audits, examples #35
C1 frames/data audit ✅ Cleared 2026-10-03 examples #24/#25 TIAGo and TALOS audits; its follow-ups #97–#99 were moved to C4 and closed there
C2 calibration truth/holdout ✅ Cleared 2026-10-05 accepted on core a991bf3 + examples c791ecd; deferred items moved to #119/#120 (C4)
C3 geometric export ✅ Cleared 2026-10-06 accepted on core efd9f69 + examples 2c75f50
W3 data/result contracts ✅ Cleared 2026-10-06 core #126 (ADR, #54), #128/#130 (contract, #55), #132 (#131), #127 (#125); examples #84 (#17); accepted on core 4ec06d4 + examples 9a9e6d7
D3 UR10 truth fixture ✅ Cleared 2026-10-07 examples #21 by examples #89/#91 (fixture, frozen protocol v1, UR10 example moved onto it); #142 by #144; #143 by #145 + examples #92 (both added 2026-10-07); accepted on core 2260786 + examples b23b836 (core 846 passed; examples validate.py 16/16, pytest 255 passed)
D5 convergence research ✅ Cleared 2026-10-10 #22 by PR #31 (revise); #30 by PR #154 (no-go: 8/24 gated fits exhaust 2000 evaluations). The method change #155 moved to LC1 as its go gate
D6 inertial export ✅ Cleared 2026-10-06 #60 by PR #138; accepted on core 0e6a78c + examples a3381bc (core 817 passed; examples validate.py 16/16, pytest 237 passed); merged-body export left to D7 (#61)
S1 reporting contract ✅ Cleared 2026-10-06 core #63 (PR #134), #70, #100, #103 (PR #135); examples #30 (examples PR #85), #36
C4 calibration reference ✅ Cleared 2026-10-06 examples #29 by examples #88 (reference_run.py); #119 by #141 (core support; TIAGo protocol keeps one marker); #120 by #140 + examples #87 (map replaces the coefficient); #97–#99 by #127, #137, #139 + examples #86; accepted on core c80b5fc + examples 88e2fc2. Held-out marker RMSE 3.8–4.2 mm; export parity ≤ 2.1e-12 m
S2 uncertainty In progress (M2) — core #107 calibration standard errors fixed; #64 open
U1 onboarding ✅ Cleared 2026-10-11 core #66 (guideline); examples #33 by examples PR #123: worked briefs for the UR10 truth and TIAGo identification references, TIAGo mocap calibration and a TX40 no-validation-data case, rerun against the accepted D7/C4 evidence on core 779e830 + examples b167298 (examples validate.py 18/18)
D4 physical comparison ✅ Cleared 2026-10-09 #59 by PR #153 (2026-10-08); examples #12 by examples PR #13; examples #22 by examples PRs #94 and #95
D7 dynamic reference ✅ Cleared 2026-10-10 #61 by PRs #165, #172; #116 by #169 + examples #117; examples #69, #68 by examples #118, #23 by examples #119 (identification_reference.py). Accepted on core 658fe99 + examples 663d642 (examples validate.py 18/18). UR10 truth and TIAGo select physical_fit; export parity ≤ 6.1e-10. Follow-ups #163 and #164 fixed by PR #174 (projected stays non-selectable)
LC1 log-Cholesky production In progress (optional) — Go gate #155 (method change) in progress: exploration done on spent seeds, method choice pending, protocol not frozen. #23–#25 and examples #11 wait on its go decision
S3, B1 Blocked — S3 and B1 wait on S2 and M1 acceptance
S4 composition (M2) Blocked — W3 cleared; still waits on accepted M1 references

Gate summary: M0's delivery roster (W1, W2, W4) and M1.1 (D1, D2, C1) are cleared. The calibration workstream is complete through M1.4 (C2, C3, C4). The dynamic workstream is complete through M1.4 (D3, D4, D6, D7), released in 0.7.0. U1 cleared on 2026-10-11.

M1 accepted (2026-10-12; review tracker #181). Evidence pair: core 779e830 + examples b167298. The maintainer ratified the closure records (R-1: W1, W2, W4, D1, D2, C1, D4, S1, D7) and accepted the #97 duplicate closure as completed via #125/#127 (C-1). Scope accepted: S-1 real-data references at execution scope (held-out error reported, not gated); S-2 TIAGo effort scale and arm_1 constant still open (examples #126); S-3 lumped TIAGo export; S-4 PAL not run on hardware; S-5 TALOS contact as a regression consumer. G-1 (a failed calibration fit could be exported) is fixed before the release candidate: core #182 by PR #187 (9dba6da on devel) and examples #124 by PR

127 (20b6377 on main).

M0 gate review accepted (2026-10-12, #181 §9). Clauses: existing core gates retained (blocking Lint, Core CI and Documentation green); examples assets and dependencies reproducible (W1); numerical regressions explained (W2); review and merge rules applied (W4); exact tested pairs cited as core fe7dc51 + examples b8d9c75 (hosted runs 37134266859 / 37136143367) and core tag v0.5.0 (02f705a). The pair is not clean for the M0 cycle: examples has no v0.5.0 tag, because pairing started at 0.6.0.

Housekeeping (2026-10-12): empty milestones (core C4 and U1, examples U1 and the W1, D2, C1 and W4 ones) are closed and the stale D1 counter was refreshed (#183, H-2). The stale status:blocked labels on core #61 and tracker #42, and on examples #23, were resolved when D7 cleared.

Log-Cholesky #30 can use the independent analytic core fixture. D1 is fixed (#69, merged 2026-10-02) and the D2 audits are complete, so real-dataset work can start with D3. Inertial export can be tested with known feasible parameters independently of solver success. Calibration need not wait for dynamic optimization, but changes to shared export/report code require paired regression coverage and serial integration.

Path forward

Status as of 2026-10-12. The trackers stay authoritative.

Critical path (M1 acceptance). D7 cleared on 2026-10-10 (steps 1–6 below, kept as its record) and U1 on 2026-10-11 (step 7); the M1 acceptance review (step 8) was completed on 2026-10-12. Steps 9–12 are what remains before 1.0.0.

Step Issue State What it needs
1 examples #69 — ship the calibration_slow and calibration_weight runs, default validation_data_file, payload scale check done (PR #103) The original 2021-07 bags and the exporter that reproduces the shipped run byte for byte. Do this first: #68's acceptance bar is held-out RMSE on calibration_slow no worse than 1.21
2 examples #68 — velocity filter model, torso/wrist/arm_1 effort handling, Hey5 URDF, constants in config done (examples PR #118) The same bags. Seven checklist items, each ships its derived data and analysis in the repository
3 core #116 — deterministic base-parameter selection done (PR #169) Independent of 1–2; can run in parallel. Lets the golden tests drop the basis-dependent masks added in PR #165
4 examples #23 — headless reference command (UR10 truth protocol with physical_fit and export; TIAGo rejected-stage and arm_7 merged-body cases) done (examples PR #119) Needs #61's library side (merged). Acceptance is V3: full validate.py
5 core #61 — close with the V2 run linked done (PRs #165, #172) Library side done in PR #165; its acceptance criteria are met, its validation level (V2) waits on step 4
6 D7 tracker #42 — closing review done (2026-10-10) Closes last, after steps 1–5 and the maintainer accepts the integration evidence
7 U1 acceptance (examples #33) done (examples PR #123) Worked briefs checked against the accepted evidence
8 M1 acceptance review (#181) done (2026-10-12) Accepted on core 779e830 + examples b167298
9 Calibration export refusal (G-1): core #182, examples #124 done (PR #187, examples PR #127) A failed fit is no longer exported silently
10 Public API and stability: core #184 open Declare the 1.0 public API
11 Deprecation removals: core #185 + examples #125 open Remove deprecated features batched into 1.0
12 RC procedure: core #186 open Release candidate, soak, then 1.0.0

After M1 acceptance (M2/M3): S2 sensitivity (core #64, examples #31), then S3 experiment design (core #65, #90, examples #32), S4 composition (core #67) and B1 backend parity (core #68, examples #34).

Found along the way (unscheduled, delivery label, no package). These did not block D7. Both were fixed by PR #174 (merged 2026-10-11) and released in 0.7.0.

Issue Defect Fix
core #163 The physical-consistency projection projected the nominal model, not the fit ✅ Projects the reconstruction; without reconstruction it is skipped and the physical stage is not_run. projected stays non-selectable
core #164 The SDP reconstruction and LMI projection passed max_seconds to picos, which only knows timelimit ✅ Passed as timelimit in both

Identification study expansion (package D8, research, status:planned, outside baseline M1). D8 groups core #157–#161 and examples #115 under milestone D8 (no tracker yet). Each extends the D4 physical comparison and none changes the baseline:

Issue Study
core #155 Change the log-Cholesky fitting method for reliable termination (belongs to LC1 as its go gate, not D8; delivery)
core #157 Geometric (log-det) regularization for the physical direct fit
core #158 Geometry-derived physical constraints (mass, CoM, bounding ellipsoid)
core #159 Manifold-optimization alternative to log-Cholesky
core #160 Noise-bias estimators (IDIM-IV, DIDIM, TLS) in the physical comparison
core #161 Bayesian physically consistent identification
examples #115 TX40: trace the identification CSVs to the original recording and ship the author's 2021 reference identification (data for #160 and the D4 comparison)
examples #70, #71 TIAGo suspension and backlash research examples; now Phase 3 of C5 (below)

Calibration study expansion (package C5, tracker core #167, status:planned). The calibration studies plan (proposed 2026-10-09) brings further studies to the TIAGo motion-capture standard. Phase 0 first, because every study uses its tools:

Phase Issue Study
0 examples #96 Shared simulation and held-out harness (confirms the identifiable-set fixes #99 and #113 hold)
1 examples #97 TIAGo Pro motion capture
1 examples #98 TALOS table contact
1 examples #99 UR10 hand-eye (k-fold within one session)
2 examples #100 TIAGo motion capture across hardware (audit first)
2 examples #101 TIAGo head camera, chessboard on hand (audit first)
3 examples #71, #70 TIAGo backlash surface and suspension base (existing issues, to be attached to C5)

C5 is separate from M1: no study depends on D7, and the TIAGo motion-capture reference numbers are its regression check. Phase 2 needs the original 2023 recordings from the maintainer.

Work-package milestones and PR boundaries

Work-package milestone rules

Each work package is a delivery milestone beneath a roadmap outcome M0–M3. M1.1–M1.4 are acceptance gates, not additional issue containers. Package IDs are stable package identifiers, distinct from GitHub issue numbers. GitHub milestones use these IDs; existing issues are reused and missing tasks have explicit owning packages. The package table below defines their roadmap mapping.

A package can be marked Cleared only when:

  1. Its reviewed issue roster is complete, including linked core and examples issues. Assign each issue one owning package; link dependencies elsewhere.
  2. Every included issue is resolved with its acceptance criteria met, its required PRs reviewed/merged, and evidence linked. Closing an issue as a duplicate, deferred or “not planned” does not satisfy that obligation.
  3. Package-level integration/acceptance evidence also passes on the declared revision pair. All issue closures alone are insufficient if the combined workflow still fails its gate.
  4. A maintainer reviews the closure record and confirms the accepted outcome.

Before Ready, record owner, roadmap gate, issue roster, dependencies, acceptance criteria and evidence location. At closure, retain issue/PR links, tested revisions, commands, report and any limitations. Status is Draft → Ready → In progress → In review → Cleared; blocked work retains its unmet dependencies. An empty draft roster cannot be treated as a completed milestone.

Deferral requires an explicit reviewed scope change: preserve the original issue and reason, move it to a named future package, and update the roadmap mapping if its exit criteria change. Do not silently remove unresolved issues to clear a package. Cross-repository milestones need one canonical roster (parent issue/project record) linking both repositories, since their individual GitHub milestone views do not provide a combined closure record.

D5 is a separate research milestone, cleared on 2026-10-10 with #22 (revise) and

30 (no-go); it was never required for the supported baseline M1 scope. The

method-change revision #155 moved to LC1 as its go gate. Promoting the nonlinear path adds #155 and #23–#25 to that path's reviewed roster; none are silently treated as completed by D7. Basic acquisition/design guidance is part of U1; S3 is the later algorithmic improvement milestone.

ID / canonical tracker Roadmap outcome / gate Outcome / justification Repository and dependencies Acceptance evidence
W1 M0; enables M1.1 Reproducible examples environment and fixtures Examples; existing PR #13 plus focused asset follow-up Clean checkout resolves required geometry; pinned sources/licenses; explicit dependency failures; no reliance on a developer ROS search path
W2 M0; enables calibration M1.1 Explain TALOS Linux/3.7 regression Examples #14, core companion only if cause is generic Capture solver status, seeds, native versions and both chains; reproduce before/after; retain current improvement gate until independently justified
W3 M1 shared contract; M2 prerequisite Working data/result contracts Proposed core ADR after inventory of both workflows Joint/order/frame/unit/timestamp provenance, observed vs reconstructed effort, masks, split IDs and optional fields; documented adapters preserve old users
D1 M1.1 dynamic Correct every tangent acceleration coordinate Core #32 Analytic final-joint regression, constant/variable dt, invalid timestamps and documented nq != nv policy; affected examples rechecked
D2 M1.1 dynamic Audit robot signal processing Separate examples issues for UR10 and TIAGo Recorded vs inferred timestamps; explicit filter rates/cutoffs/order; torque/current units/signs; trim/decimation index provenance; immutable raw files
D3 M1.2 dynamic Fresh UR10 truth fixture and benchmark protocol Examples; D1/D2 Save verified true inertias, analytic q/dq/ddq, independent train/validation trajectories and noise seeds; no ground-truth parameter claims from old CSVs
D4 M1.2 dynamic Fair physical-estimation comparator Private core spike + linked examples experiment; D3 Base OLS, exact reconstruction, direct LMI-constrained effort fit, per-link projection and log-Cholesky; common inputs; comparable objectives and extras policy; separate failures
D5 M1.2 optional nonlinear research Convergence/scaling revision Core #22 (revise), #30 (no-go); cleared 2026-10-10, #155 moved to LC1 Objective/gradient histories, scaling/bounds/prior ablations, multiple starts and justified budget; preserve earlier protocol; the #30 go gates, carried unchanged into #155, govern go
D6 M1.3 dynamic Complete inertial export Core; prior mapping review and known-parameter fixture Mass/first moments/CoM, origin vs CoM tensor and inertial rotation handled; export/reload matches intended RNEA and physical verdict; unsupported targets fail explicitly
D7 M1.4 dynamic Accepted dynamic reference workflow Core integration + examples; D4/D6/S1; D5 only for optional nonlinear path Explicit selected stage, fit and genuine validation splits, per-joint units, physical/solver verdict, exported model and archive; successful supported baseline can ship without nonlinear go
C1 M1.1 calibration Audit geometric data/frames and reproduction Examples with focused core fixes; W1/W2 Named observation frames, translation/rotation units, timestamps, measurement source and split policy; TIAGo and TALOS current behavior captured
C2 M1.2 calibration Calibration synthetic truth + real held-out reference Examples; C1 Known synthetic corrections recovered in identifiable coordinates; held-out pose/contact errors on unused postures; diagnose gauge, priors and solver failures
C3 M1.3 calibration Validate redistribution and geometric export Existing core QR/export helpers + examples; C2 Calibrated-model FK matches exported/reloaded model; parameter/frame semantics retained; PAL runtime YAML checked where relevant; metrology frames are not silently embedded
C4 M1.4 calibration One accepted calibration reference workflow Examples TIAGo mocap selected; C2/C3/S1 One command, training/held-out report, identifiable vs redistributed corrections, export and archive; contact-only evidence labeled separately from full pose metrology
S1 M1.4 shared reporting prerequisite Minimum reporting contract Existing core report/archive modules; W3; enables D7/C4 Separate solver/data/fit/physical/export verdicts, explicit failed/fallback stages, paired revisions/hashes, old result compatibility
S2 M2 follow-up diagnostics Sensitivity and uncertainty Core diagnostics + examples; stable D7/C4 Noise/initialization trials, singular spectrum and parameter correlations; observable combinations reported; no unjustified full-parameter certainty
S3 M2 follow-up experiment design Improved experiment design Existing optimal/ + examples; S2 Compare excitation/posture selection with a frozen baseline under declared constraints; improve independent validation evidence rather than only matrix condition
W4 M0 Engineering process and regression coverage Both repositories; existing validation/contribution rules Reviewed workflow changes, focused legacy lint/mock coverage issues, reproducible checks; claimed CI automation verified on hosted runs
U1 M1.4 shared onboarding General robot/dataset guide and worked briefs Core docs + examples; draft now, acceptance uses D7/C4 Fresh dynamic and TIAGo mocap walkthroughs plus missing-data case; supported commands, methods and limitations verified
S4 M2 composition Selective reusable regressor/residual composition Core + two examples consumers; W3 and accepted M1 references Narrow ADR, two consumers, legacy numerical parity and additive compatibility; no broad refactor prerequisite
B1 M3 Backend capability/parity review Core backends//integration/; accepted reference workflow Actual backend selection or explicit rejection, supported operations matrix, same model/state comparisons and export/validation parity

Potential new work must not duplicate #20/#22–#25/#30/#32 or examples

11/#12/#14. If one package contains independent defects, split them into

individual issues/PRs rather than closing a broad issue with partial evidence.

GitHub delivery register

Milestones and their canonical rosters were created on 2026-10-02. Open each tracker for its complete issue roster, dependency links and acceptance evidence. Core trackers combine both repositories; GitHub milestone percentages are local to a repository and do not supersede the closure review. No due dates or automatic merging are configured by this setup.

Package Core milestone Examples milestone
W1 Open milestone Open milestone
W2 Open milestone Open milestone
W3 Open milestone Open milestone
D1 Open milestone No examples-owned issues in this roster
D2 Open milestone Open milestone
D3 Open milestone Open milestone
D4 Open milestone Open milestone
D5 Closed milestone No examples-owned issues in this roster
D6 Open milestone No examples-owned issues in this roster
D7 Open milestone Open milestone
C1 Open milestone Open milestone
C2 Open milestone Open milestone
C3 Open milestone Open milestone
C4 Open milestone Open milestone
S1 Open milestone Open milestone
S2 Open milestone Open milestone
S3 Open milestone Open milestone
W4 Open milestone Open milestone
U1 Open milestone Open milestone
S4 Open milestone No examples-owned issues in this roster
B1 Open milestone Open milestone
C5 Open milestone Open milestone
D8 (no tracker yet) Open milestone Open milestone
LC1 Open milestone Open milestone

C5 (calibration studies, tracker core #167) and D8 (identification studies, core #157–#161) were added on 2026-10-09 beneath M2 and are outside baseline M1 closure. Their milestones were created on 2026-10-10. Each data transfer is its own examples issue: C5 examples #104–#114 (sub-issues of their studies), D8 examples #115 (sub-issue of core #160).

LC1 uses existing core #20 as the canonical conditional-production tracker for core #23–#25 and examples #11. Its go gate is research issue #155 (moved from D5 on 2026-10-10); a go decision there is a dependency, not completion of those production issues. LC1 is outside baseline M1 closure and introduces no additional production scope.

Initial queue (2026-10-02): D1 / core #32 was the first ready correctness fix, delivered by #69. W1, W2, W3, W4, D1, D2, D3, D6, C1, C2, C3, C4 and S1 have since cleared (see implementation status). Current queue (2026-10-12): calibration and dynamic references are both done through M1.4 (C4, D7; released in 0.6.0 and 0.7.0), U1 cleared on 2026-10-11 and M1 was accepted on 2026-10-12. The critical path is the 1.0 work (see the path forward). On the optional path, D5 cleared (#30 no-go) and LC1's go gate #155 (method change) is in progress. Select one issue, validate its focused change, open its PR, then await review/merge approval.

Experimental design decisions to review before coding

Dynamic identification

Use two comparison levels. The first holds identical training-estimated extras fixed to isolate inertial estimation; the second jointly estimates physical extras where supported. Do not rank a joint solver against a frozen-extra solver as though only parameterization changed. Define per-joint residual scaling from training noise/units if whitening is proposed, and first retain an unweighted compatibility baseline. TIAGo force and torque cannot become one unlabeled physical RMSE.

Full SDP equality reconstruction preserves an estimated base vector; direct constrained effort fitting may change it; per-link projection may change both base fit and effort. Each needs its own objective, success definition and stage label. Boundary solutions and massless fixed links need explicit policy. No API is chosen just because one research script already contains a function.

Freeze ranks/tolerances, bounds, noise, initialization, iteration/evaluation budget, timeout and quality metrics before measuring. Preserve the old protocol. The existing #30 criteria (carried into #155) are not relaxed by this plan; any revised criterion requires a reasoned decision before new measurements.

Calibration

TIAGo mocap is the user-selected first real reference because existing redistribution and runtime-export support can be reused. TALOS table-contact remains a second consumer and a regression target, not a substitute for full 6D ground truth. Use held-out postures/recordings with no fit-stage leakage. Address gauge/frame ambiguity before interpreting individual geometric corrections or covariance. Assess translated and rotational residuals separately unless a justified measurement covariance defines a common whitened residual.

New camera/eye-hand, multi-marker or suspension features are candidates for a separate reviewed scope after the reference baseline; they are not implicitly included in this iteration. Historical port documents must be re-audited.

General onboarding pipeline alongside the references

The two reference workflows are demonstrations, not the only supported route for users. Add a reusable decision pipeline for any new robot/dataset without creating a new runtime orchestration API in this planning phase:

  1. Inventory available models, sensors, timestamps, measured/derived channels and independent validation; record missing information.
  2. Define the application, observation model, parameter blocks, fixed quantities, gauge and limits on what the data can identify.
  3. Select supported baseline/candidate methods by objective, constraints and noise/prior assumptions; label research paths separately.
  4. Design acquisition and final validation together, reviewing excitation, observation coverage, feasibility and collection constraints.
  5. Preserve raw measurements; audit clocks, units, frames, synchronization, derivatives/filter rates and raw-to-processed indices.
  6. Fit under a frozen protocol; interpret training fit, observability, physical feasibility and solver termination separately.
  7. Evaluate unused data, inspect computed/skipped verification checks, validate exported-model parity and archive reproducible evidence.

Core docs/source/example_workflow.md owns this scientific decision guide. Existing task tutorials link to it and retain task-specific runnable material. Examples docs/new-example-guide.md owns repository integration and docs/experiment-brief-template.md provides a human-readable record copied into examples/<robot>/EXPERIMENT.md. This is not a new YAML schema or an enforced runtime contract. Robot README/data notes own actual measurements and commands; CONTRIBUTING owns contributor/review rules.

Work-package milestone U1 — general user onboarding runs alongside D7/C4. Draft the guide now; validate it later by walking through one fresh dynamic example and TIAGo mocap, plus a missing-data case. Acceptance means the brief leads to an explicit model/method choice, reproducible processing and applicable validation without relying on undocumented reference assumptions. Check that supported commands/links match the accepted core/examples revisions; label unimplemented methods and missing evidence. Do not add an interactive wizard, new config keys or generated acquisition code without separate review.

Round 2 reviews the brief's questions and evidence requirements alongside the data/result contracts. Reference delivery PRs provide worked briefs and expose where the generic guide needs correction. U1 does not wait for backend expansion or a successful research-only log-Cholesky integration.

Repository and documentation organization

Preserve existing directories and user entry points. Do not move datasets, robot helpers or broad packages as a prerequisite to fixing known defects.

  • Core ROADMAP.md: milestone order, priorities and exit criteria; one canonical file embedded by the docs site. Stable M0–M3 IDs remain.
  • Core docs/plans/: this active execution proposal; archive/ keeps old plans. Add an index with explicit Draft/Accepted/Historical status.
  • Core docs/decisions/: narrow ADRs for new schemas/interfaces/objectives. Link to existing decisions rather than duplicating their reasoning.
  • Core docs/development/: dated audits and validation evidence; private spikes remain marked experimental. Architecture changes only after facts change.
  • Examples benchmarks/: research protocol, comparisons, curated small result records and dated reports. Preserve old protocols and source hashes.
  • Examples examples/<robot>/: runnable supported recipes and robot data/config notes. Large generated runs remain outside source control or in CI artifacts.
  • Each repository CONTRIBUTING.md: its execution/PR instructions. Core owns the shared rules; examples documents exact commands, dependency pairing, fixtures and its main PR target rather than copying the whole core workflow.

Existing examples .github/ ignore rules and local-only CI material need a focused tracked-file audit before adding more automation. A local file or passing local test is not proof that it is tracked or executed remotely.

Proposed development workflow improvements

These amendments are for review; CONTRIBUTING/AGENTS are not silently replaced by this draft. Retain the established one-issue/one-PR rule and explicit merge approval. Suggested additions:

  1. Discussion before implementation. Agree on scope and acceptance evidence; approve public contracts through an ADR. Separate “approve plan,” “implement,” and “merge.” A research revise decision cannot be interpreted as API approval.
  2. Issue readiness. Classify numerical bug, asset/dependency problem, research, API feature or maintenance. State core/examples owner, dependencies, current reproducer, immutable inputs, proposed tests and out-of-scope work. Avoid creating all speculative issues at once.
  3. Focused branches. Core branches from current devel; examples from main. Keep discussion/report changes out of unrelated numerical PRs. Record tested core/examples commit pairs. Prefer isolated worktrees when an open PR is already using the main checkout.
  4. Before/after evidence. Run a reproducer on baseline and changed revisions. Report command/exit code and classify data validity, solver convergence, physical consistency, held-out quality and export fidelity separately.
  5. Validation tiers. V0 hooks/docs for documentation; V1 core tests for code; V2 affected examples for data/numerics/API; V3 both reference workflows and export invariants for milestone/release. Examples retains full validate.py phase checks and known-failure evidence. A failure cannot be hidden by a skip.
  6. CI organization. Fast core checks plus Pinocchio 3.7/4.1 profiles; examples deterministic fixtures/smokes and dataset jobs with reproducible assets. Slow IPOPT/full workflow checks can be separately scheduled/manual, retaining their failure/timeout statuses. Collect research artifacts on failure without marking a failed regression green. This is a proposed CI split, not deployed.
  7. Review and merge. Open each completed issue's focused PR. Maintainer reviews; merge only after explicit approval and required checks on the current head. Material scope changes require renewed review. No automatic merging.
  8. Post-merge cleanup. Synchronize base branches; remove that PR's merged remote/local feature branch and worktree after checking for uncommitted or unique commits. Keep main/devel/releases and unrelated ancient branches.
  9. Release evidence. An accepted method and passing CI are insufficient: verify supported examples, exported model reloads, archived reports, version metadata and dependency pair. Version/tag/publishing remains separate review.

Recommended issue metadata: type, area, priority, milestone, dependency links, research/production designation and acceptance evidence. Recommended states: Draft → Ready → In progress → In review → Done, with Blocked carrying its actual dependency. Readiness labels and milestone/issue rosters are established by the approved tracker setup. They are maintained manually; GitHub Project automation and server-enforced branch rules are not implied.

Review rounds and bounded implementation batches

Round 1 — this proposal

Review the two parallel outcomes, package ownership, calibration reference, method comparison boundaries and proposed sequence. Revise roadmap/plan locally. The subsequent user instruction explicitly authorized tracker creation. No code changes, commits/pushes or merges follow merely from accepting the plan.

Round 2 — contracts and frozen protocol

Inventory current data/results and propose the smallest compatible extension. Review each numerical objective, extras/weighting policy, exports and failure semantics. Decide what metrics and datasets can actually establish. Update narrow ADRs and the benchmark protocol before approving implementation.

Round 3 — first delivery batch

Select only ready work: existing core #32 (delivered by #69); reproducible example asset fixes; existing examples #14; separate robot sampling audits. Calibration frame audit can proceed in parallel. Done (2026-10-03): this batch cleared as D1, W1, W2, D2 and C1, together with W4. Open focused issues for the approved missing work. Each completed issue produces a PR for review; dependent work waits or uses an explicit tested commit pair. Review evidence before expanding the batch.

Later batches

Fresh UR10 truth fixture and calibration truth/held-out fixture; physical solver comparison and #30; independent inertial/geometric export gates; then dynamic and calibration reference integration. Each batch ends with an evidence review, not a guessed calendar deadline. Estimates follow a scoped issue audit; no release date or package version is promised in this draft. Progress at 2026-10-06: the calibration batches (C2, C3, C4) and inertial export (D6) have cleared; the UR10 truth fixture (D3) cleared on 2026-10-07; the physical comparison (D4) cleared on 2026-10-09.

Decisions still open

Calibration order is settled for this draft: TIAGo mocap first, TALOS contact second. The following choices still need review:

  1. Should the first joint physical estimator include bounded/positive friction and actuator parameters, or limit the initial comparison to fixed extras?
  2. Which independent real recordings are available for final acceptance?
  3. What is the minimum supported result/data extension after adapter inventory?
  4. What measured physical boundary policy and export failure behavior should the public API expose?

Proposed remaining defaults: fixed-extra comparison followed by a separate joint-estimation comparison; no claims of independent real validation until recordings exist; additive compatibility adapters; failed/nonphysical stages cannot silently become the selected exported model.